20 tracked · by stage: Under review 13 · EDA 5 · MOU 2 · updated 2026-09-08
| Project | Stage | Technology | Source |
|---|---|---|---|
| EST FERMI ENERGIA BWRX300 BWRX-300 (6 Units) Site Selection Process Begins, Initial Site Evaluation 2025-2027, Construction Permit Appli | EDA | SMR | 📎 Power Limited DB |
| EST FERMI BWRX300 BWRX-300 Deployment: Construction by 2030, Operation by 2035-2036, Second SMR 12-16 Months Later | EDA | SMR | 📎 Power Limited DB |
| EST SAMSUNG BWRX300 BWRX-300 Feasibility Study Until April 2026, Including Latvia and Lithuania | EDA | SMR | 📎 Power Limited DB |
| Aidu-Liiva, Ida-Viru州 SMR Candidate Site Permit Application Submitted, National Plan Application Expected 2024 | EDA | SMR | 📎 Power Limited DB |
| Letipea, Aidu Four 300MW SMRs Planned, First Unit Online by 2031, Technology Selection in February | EDA | SMR | 📎 Power Limited DB |
| ESTONIA SMR NATIONAL PROGRAM Estonia Considers SMRs for Oil Shale Phase-out, 2050 Net-Zero; IAEA INIR Mission Praises Nuclear Infrastructur | Under review | SMR | 📎 World Nuclear News |
| Estonia Rolls-Royce, Fermi Energia MoU for SMR Feasibility Study in Estonia | Under review | SMR | 📎 World Nuclear News |
| EST GOV NUCLEAR LAW Nuclear Energy Safety Act Passes First Review | Under review | SMR | 📎 Power Limited DB |
| EST ESTONIA NUCLEARFRAMEWORK Draft TEOS (Nuclear Energy & Safety Act) Submitted to Parliament, Effective January 2027 | Under review | Undecided (Policy stage) | 📎 Power Limited DB |
| EST ESTONIA NUCLEAR 120 Million Euros in Public Funds for Nuclear Program Over Next Decade, IAEA Review Underway | Under review | Undecided (Policy stage) | 📎 Power Limited DB |
| EST GOVERNMENT SMR 61% of Public Favors Nuclear Power Introduction: May 2024 Poll | Under review | SMR | 📎 Power Limited DB |
| EST KLIIMAMINISTEERIUM SMR Parliamentary Decision Urged on Nuclear Task Force Report, Projecting €5.5M-€19M Annual Revenue Increase | Under review | Undecided (Policy stage) | 📎 Power Limited DB |
| EST IAEA NuclearReadiness IAEA Expert Team Assessing Nuclear Power Potential, Final Report Due End of Year | Under review | Undecided (Policy stage) | 📎 Power Limited DB |
| EST ESTONIA NUCLEAR LAW Legal Consultation Progressing for Nuclear Act & Regulatory Structure Development | Under review | Undecided (Policy stage) | 📎 Power Limited DB |
| EST ESTONIA LEGISLATION Consultation Underway for Nuclear Act Enactment & Regulatory System Establishment | Under review | Undecided | 📎 Power Limited DB |