80 tracked · by stage: Under review 47 · EDA 12 · FEED 8 · Operating 6 · MOU 3 · Construction 2 · updated 2026-10-24
| Project | Stage | Technology | Source |
|---|---|---|---|
| Kozloduy 20-year maintenance and I&C system aging management contract for VVER-1000 Units 5 and 6 | Operating | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy Alternative supply chain for Russian nuclear fuel established; 10-year contract signed for 5.7 million pounds | Operating | Restart | 📎 Power Limited DB |
| Kozloduy 10-year fuel supply contract signed for Kozloduy Unit 5 to replace Russian fuel | Operating | Restart | 📎 Power Limited DB |
| Kozloduy Unit 5 scheduled preventive maintenance underway | Operating | Restart | 📎 Power Limited DB |
| Kozloduy Laurentis–CNPSA–BWXT Consortium Signs Owner's Engineer Contract Worth Hundreds of Millions of Euros for Two Ne | Construction | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy New Kozloduy Units 7 and 8 planned; Unit 7 commercial operation scheduled for 2035; nuclear cooperation agreem | Construction | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy Two AP1000 units: FID expected in the second half of 2026; project cost of $14 billion; localization target ab | FID | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy Design contract signed for two AP1000 units (Units 7 and 8); operation scheduled for 2035 and 2037 | FEED | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy Engineering contract extended by 14 months; first concrete targeted for 2030 | FEED | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy FEED contract extended for two AP1000 units (Units 7 and 8); Hyundai E&C selected as preferred bidder; commerc | FEED | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy AP1000 supply chain expanded; component and service MOUs signed with 17 Bulgarian companies | FEED | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy Two New AP1000 Units Target Commercial Operation in 2035; Hyundai Engineering & Construction Selected as Prefe | FEED | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy Hyundai Engineering & Construction selected as sole qualified bidder for Kozloduy Units 7 and 8 construction; | FEED | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy Unit 7 Targets Completion in 2033, Unit 8 Two to Three Years Later; 2,300 MW of New Capacity | FEED | Large Nuclear Plant | 📎 Power Limited DB |
| Kozloduy FEED Contract Signed for One or Two AP1000 Units; Existing Site Infrastructure Assessment Underway | FEED | Large Nuclear Plant | 📎 Power Limited DB |